|
Introduction
Project financing
is an innovative and timely financing technique that
has been used on many high-profile corporate projects, including Euro
Disneyland and the Eurotunnel. Employing a carefully engineered
financing mix, it has long been used to fund large-scale natural
resource projects, from pipelines and refineries to electric-generating
facilities and hydro-electric projects. Increasingly, project financing
is emerging as the preferred alternative to conventional methods of
financing infrastructure and other large-scale projects worldwide.
Project Financing discipline includes
understanding the rationale for
project financing, how to prepare the
financial plan, assess the risks,
design the financing mix, and raise the funds. In addition, one must
understand the cogent analyses of why some project financing plans have
succeeded while others have failed. A knowledge-base is required
regarding the design of contractual arrangements to support project
financing; issues for the host government legislative provisions,
public/private infrastructure partnerships, public/private financing
structures; credit requirements of lenders, and how to determine the
project's borrowing capacity; how to prepare cash flow projections and
use them to measure expected rates of return; tax and accounting
considerations; and analytical techniques to validate the project's
feasibility.
Project finance is finance for a particular project, such as a mine,
toll road, railway, pipeline, power station, ship, hospital or prison,
which is repaid from the cash-flow of that project. Project finance is
different from traditional forms of finance because the financier
principally looks to the
assets and revenue of the project in order to
secure and service the loan. In contrast to an ordinary borrowing
situation, in a project financing the financier usually has little or no
recourse to the non-project assets of the borrower or the sponsors of
the project. In this situation, the credit risk associated with the
borrower is not as important as in an ordinary loan transaction; what is
most important is the identification, analysis, allocation and
management of every risk associated with the project.
The
purpose of this paper is to explain, in a brief and general way, the
manner in which risks are approached by financiers in a
project finance
transaction. Such risk minimization lies at the heart of project
finance.
In a
no recourse or limited recourse project financing, the risks for a
financier are great. Since the loan can only be repaid when the project
is operational, if a major part of the project fails, the financiers are
likely to lose a substantial amount of money. The assets that remain are
usually highly specialized and possibly in a remote location. If
saleable, they may have little value outside the project. Therefore, it
is not surprising that financiers, and their advisers, go to substantial
efforts to ensure that the risks associated with the project are reduced
or eliminated as far as possible. It is also not surprising that because
of the risks involved, the cost of such finance is generally higher and
it is more time consuming for such finance to be provided.
Risk
minimization process
Financiers are concerned with minimizing the dangers of any events which
could have a negative impact on the financial performance of the
project, in particular, events which could result in: (1) the project
not being completed on time, on budget, or at all; (2) the project not
operating at its full capacity; (3) the project failing to generate
sufficient revenue to service the debt; or (4) the project prematurely
coming to an end.
The
minimization of such risks involves a three step process. The first step
requires the identification and analysis of all the risks that may bear
upon the project. The second step is the allocation of those risks among
the parties. The last step involves the creation of mechanisms to manage
the risks.
If a
risk to the financiers cannot be minimized, the financiers will need to
build it into the interest rate margin for the loan.
STEP 1 - Risk identification and analysis
The
project sponsors will usually prepare a feasibility study, e.g. as to
the construction and operation of a mine or pipeline. The financiers
will carefully review the study and may engage independent expert
consultants to supplement it. The matters of particular focus will be
whether the costs of the project have been properly assessed and whether
the cash-flow streams from the project are properly calculated. Some
risks are analyzed using financial models to determine the project's
cash-flow and hence the ability of the project to meet repayment
schedules. Different scenarios will be examined by adjusting economic
variables such as inflation, interest rates, exchange rates and prices
for the inputs and output of the project. Various classes of risk that
may be identified in a project financing will be discussed below.
STEP
2 - Risk allocation
Once
the risks are identified and analyzed, they are allocated by the parties
through negotiation of the contractual framework. Ideally a risk should
be allocated to the party who is the most appropriate to bear it (i.e.
who is in the best position to manage, control and insure against it)
and who has the financial capacity to bear it. It has been observed that
financiers attempt to allocate uncontrollable risks widely and to ensure
that each party has an interest in fixing such risks. Generally,
commercial risks are sought to be allocated to the private sector and
political risks to the state sector.
STEP
3 - Risk management
Risks must be also managed in order to minimize the possibility of the
risk event occurring and to minimize its consequences if it does occur.
Financiers need to ensure that the greater the risks that they bear, the
more informed they are and the greater their control over the project.
Since they take security over the entire project and must be prepared to
step in and take it over if the borrower defaults. This requires the
financiers to be involved in and monitor the project closely. Such
risk
management is facilitated by imposing reporting obligations on the
borrower and controls over project accounts. Such measures may lead to
tension between the flexibility desired by borrower and risk management
mechanisms required by the financier.
Types of risks
Of
course, every project is different and it is not possible to compile an
exhaustive list of risks or to rank them in order of priority. What is a
major risk for one project may be quite minor for another. In a vacuum,
one can just discuss the risks that are common to most projects and
possible avenues for minimizing them. However, it is helpful to
categories the risks according to the phases of the project
within which
they may arise: (1) the design and construction phase; (2) the operation
phase; or (3) either phase. It is useful to divide the project in this
way when looking at risks because the nature and the allocation of risks
usually change between the construction phase and the operation phase.
1. Construction phase risk - Completion risk
Completion risk allocation is a vital part of the risk allocation of any
project. This phase carries the greatest risk for the financier.
Construction carries the danger that the project will not be completed
on time, on budget or at all because of technical, labor, and other
construction difficulties. Such delays or cost increases may delay loan
repayments and cause interest and debt to accumulate. They may also
jeopardize contracts for the sale of the project's output and supply
contacts for raw materials.
Commonly employed mechanisms for minimizing completion risk before
lending takes place include: (a) obtaining completion guarantees
requiring the sponsors to pay all debts and liquidated damages if
completion does not occur by the required date; (b) ensuring that
sponsors have a significant
financial interest in the success of the
project so that they remain committed to it by insisting that sponsors
inject equity into the project; (c) requiring the project to be
developed under fixed-price, fixed-time turnkey contracts by reputable
and financially sound contractors whose performance is secured by
performance bonds or guaranteed by third parties; and (d) obtaining
independent experts' reports on the design and construction of the
project. Completion risk is managed during the loan period by methods
such as making pre-completion phase drawdown’s of further funds
conditional on certificates being issued by independent experts to
confirm that the construction is progressing as planned.
2. Operation phase risk - Resource / reserve risk
This
is the risk that for a mining project, rail project, power station or
toll road there are inadequate inputs that can be processed or serviced
to produce an adequate return. For example, this is the risk that there
are insufficient reserves for a mine, passengers for a railway, fuel for
a power station or vehicles for a toll road.
Such
resource risks are usually minimized by: (a) experts' reports as to the
existence of the inputs (e.g. detailed reservoir and engineering reports
which classify and quantify the reserves for a mining project) or
estimates of public users of the project based on surveys and other
empirical evidence (e.g. the number of passengers who will use a
railway); (b) requiring long term supply contracts for inputs to be
entered into as protection against shortages or price fluctuations (e.g.
fuel supply agreements for a power station); (c) obtaining guarantees
that there will be a minimum level of inputs (e.g. from a government
that a certain number of vehicles will use a toll road); and (d) "take
or pay" off-take contacts which require the purchaser to make minimum
payments even if the product cannot be delivered.
Operating risk
These are general risks that may affect the cash-flow of the project by
increasing the operating costs or affecting the project's capacity to
continue to generate the quantity and quality of the planned output over
the life of the project. Operating risks include, for example, the level
of experience and resources of the operator, inefficiencies in
operations or shortages in the supply of skilled labor. The usual way
for minimizing operating risks before lending takes place is to require
the project to be operated by a reputable and financially sound operator
whose performance is secured by performance bonds. Operating risks are
managed during the loan period by requiring the provision of detailed
reports on the operations of the project and by controlling cash-flows
by requiring the proceeds of the sale of product to be paid into a
tightly regulated proceeds account to ensure that funds are used for
approved operating costs only.
Market / off-take risk
Obviously, the loan can only be repaid if the product that is generated
can be turned into cash. Market risk is the risk that a buyer cannot be
found for the product at a price sufficient to provide adequate
cash-flow to service the debt. The best mechanism for minimizing market
risk before lending takes place is an acceptable forward sales contact
entered into with a financially sound purchaser.
3. Risks common to both construction and operational phases
Participant / credit risk
These are the risks associated with the sponsors or the borrowers
themselves. The question is whether they have sufficient resources
to
manage the construction and operation of the project and to efficiently
resolve any problems which may arise. Of course, credit risk is also
important for the sponsors' completion guarantees. To minimize these
risks, the financiers need to satisfy themselves that the participants
in the project have the necessary human resources, experience in past
projects of this nature and are financially strong (e.g. so that they
can inject funds into an ailing project to save it).
Technical risk
This
is the risk of technical difficulties in the construction and operation
of the project's plant and equipment, including latent defects.
Financiers usually minimize this risk by preferring tried and tested
technologies to new unproven technologies. Technical risk is also
minimized before lending takes place by obtaining experts reports as to
the proposed technology. Technical risks are managed during the loan
period by requiring a maintenance retention account to be maintained to
receive a proportion of cash-flows to cover future maintenance
expenditure.
Currency risk
Currency risks include the risks that: (a) a depreciation in loan
currencies may increase the costs of construction where significant
construction items are sourced offshore; or (b) a depreciation in the
revenue currencies may cause a cash-flow problem in the operating phase.
Mechanisms for minimizing resource include: (a) matching the currencies
of the sales contracts with the currencies of supply contracts as far as
possible; (b) denominating the loan in the most relevant foreign
currency; and (c) requiring suitable foreign currency hedging contracts
to be entered into.
Regulatory / approvals risk
These are risks that government licenses and approvals required to
construct or operate the project will not be issued (or will only be
issued subject to onerous conditions), or that the project will be
subject to excessive taxation, royalty payments, or rigid requirements
as to local supply or distribution. Such risks may be reduced by
obtaining legal opinions confirming compliance with applicable laws and
ensuring that any necessary approvals are a condition precedent to the
drawdown of funds.
Political risk
This is the danger of political or financial instability in the host
country caused by events such as insurrections, strikes, suspension of
foreign exchange, creeping expropriation and outright nationalization.
It also includes the risk that a government may be able to avoid its
contractual obligations through sovereign immunity doctrines. Common
mechanisms for minimizing political risk include: (a) requiring host
country agreements and assurances that project will not be interfered
with; (b) obtaining legal opinions as to the applicable laws and the
enforceability of contracts with government entities; (c) requiring
political risk insurance to be obtained from bodies which provide such
insurance (traditionally government agencies); (d) involving financiers
from a number of different countries, national export credit agencies
and multilateral lending institutions such as a development bank; and
(e) establishing accounts in stable countries for the receipt of sale
proceeds from purchasers.
Force majeure risk
This
is the risk of events which render the construction or operation of the
project impossible, either temporarily (e.g. minor floods) or
permanently (e.g. complete destruction by fire). Mechanisms for
minimizing such risks include: (a) conducting due diligence as to the
possibility of the relevant risks; (b) allocating such risks to other
parties as far as possible (e.g. to the builder under the construction
contract); and (c) requiring adequate insurances which note the
financiers' interests to be put in place.
Conclusion
This paper only gives a brief overview of the common risks and methods
of risk minimization employed by financiers in project finance
transactions. As stated previously, each project financing is different.
Each project gives rise to its own unique risks and hence poses its own
unique challenges. In every case, the parties - and those advising them
- need to act creatively to meet those challenges and to effectively and
efficiently minimize the risks embodied in the project in order to
ensure that the project financing will be a success.
|